Pursuit to RC's EXEC decision and construction cost estimate. The podium portion will keep using terracotta panels while tower change to metal panel.

The Challenge of the exterior wall's development lies in the the playful contrast between the various exterior materials and how their curvature, color and joints can harmony blend in the New York's skyline.

After studied several window system options which aimed to address the fluid exterior  feeling, owner signed off the zero sightline, structrually glazed hybrid wall system with outswing awning vents. The intent of this configuration is to max out the contrast of glass plain with the curvature vertical cladding.

 

NYC ECC compliance and zone green deductable

200507 Facade Presentation 11by 17 inch-
200507 Facade Presentation 11by 17 inch-
200507 Facade Presentation 11by 17 inch-
200507 Facade Presentation 11by 17 inch-
200507 Facade Presentation 11by 17 inch-
BUTCHER TOWN 5.jpg
190814 Window Options-2.jpg
190814 Window Options-12.jpg
190911 Facade Presentation  screen-3.jpg
190911 Facade Presentation  screen-2.jpg
35 10th A-201.jpg
35 10th A-202.jpg
1372 Ext Material Designations_200319.jp
400s update-1.jpg
400s update-2.jpg
400s update-3.jpg
400s update-4.jpg
400s update-5.jpg
400s update-8.jpg
400s update-10.jpg
400s update-11.jpg
FM 101.jpg
FM 201.jpg
FM 401.jpg
SK-871 35TH 10TH VMU PMU-1.jpg
SK-871 35TH 10TH VMU PMU-4.jpg
SK-871 35TH 10TH VMU PMU-3.jpg
SK-871 35TH 10TH VMU PMU-6.jpg

Click Icon to view all DOB Package.

 

zoning and energy light air-1.jpg
zoning and energy light air-5.jpg
zoning and energy light air-11.jpg
zoning and energy light air-18.jpg
zoning and energy light air-7.jpg
NBK Proposal Drawings - 35th & 10th Av4-
NBK Proposal Drawings - 35th & 10th Av4-
NBK Proposal Drawings - 35th & 10th Av4-
190609 35th-10th -Related -Proposal set
190609 35th-10th -Related -Proposal set
190609 35th-10th -Related -Proposal set
1372 -13.jpg
1372 -12.jpg
1372 -14.jpg
1372 -27.jpg
bottom of page